The Hawaiʻi County Department of Public Works announced that subsurface utility locating work will be performed as part of the Kīlauea Avenue/Keawe Street rehabilitation project beginning on Monday, April 3. The public may encounter lane closures and/or detour routing at intersections within the construction area.
A tentative schedule is listed below. Updated information can be found on the DPW website.
|
INTERSECTION |
START DATE |
DETOUR ROUTES |
Waiānuenue Ave |
April 3 |
Wailuku Drive or Haili St |
Kalakaua St |
April 6 |
Waiānuenue Ave or Haili St |
NO WORK |
April 7 – 16 |
NO WORK |
Kalakaua St |
April 17 |
Waiānuenue Ave or Haili St |
Haili St |
April 20 |
Kalakaua St or Waiānuenue Ave |
Furneaux Lane |
April 24 |
Haili St, Kilauea Av and Mamo St |
Mamo St |
April 26 |
Haili St, Furneaux Lane, Kilauea Ave |
Ponahawai St |
April 28 |
Punahoa St, Mamo St and Kilauea Ave. Kamehameha Avenue and left on Mamo St. |